CASE STUDY - CASE STUDY - Belfast Waterfront Conference & Exhibition Centre
Braecom Project Manager
- Client Side Project Manager for BCC (seconded from SIB)
Timescales: December 2012 - May 2016
Value: £30 million
Form of Contract: NEC3 ECC Option A (Design & Build from R.I.B.A. Stage E)
Key Funders: Belfast City Council, Tourism NI, (E.R.D.F.)
Floor Area G.I.F.A 9250m2 - Nett Usable Area 5500m2
BREEAM Target - Very Good
Project Delivery on Programme: Timescales 36 months
Project Delivered on Budget £30.0mill


The £30 million extension to the Belfast Waterfront Hall has transformed the existing venue into a world-class conference and exhibition facility. The extended facilities together with the Waterfront's existing auditorium and studio are expected to attract 55,000 conference delegates per annum. A purpose indoor built link to Hilton Hotel was constructed as part of the project to allow a fully integrated delegate experience.

The first major conference inside the new facilities is scheduled for Spring 2016 (the annual International Surgical Congress of the Association of Surgeons of Great Britain and Ireland).

The Conference & Exhibition Centre has been built on a restricted riverside city centre site and has been delivered under the stringent operational requirements of the live venue and neighbouring 5 star hotel. Extended facilities include:

* * * 2 x interconnecting multifunctional and highly serviced conference & exhibition halls and associated concourses
-Hall 1 - 1850 m2 11.0m high - (sub divisible into 4no halls)
-Hall 2 - 750 m2 5.0m high - (sub divisible into 4no halls)
*
* * * 9 x additional flexible meeting room facilities catering for delegate groups of between 35 - 200
*
* * * Dedicated registration & reception space - 550m2
*
* * * Fully equipped CPU kitchen, satellite kitchens and associated dry, cold & chilled storage and capable of catering for banqueting for 750-1000 delegates.
*
* * * Maximum integration of existing facility including retention of 320 seat Studio theatre, bars and cafe.
*
* * * Purpose designed technical fit out.
*
* * * Exterior terraces offering stunning views of the River Lagan.
*
Project delivered under Construction excellence guidelines including the management and chairing of Project Steering Group meetings, reporting & representation to the Project Board (monthly) on Programme, Costs, Funding, Quality & Risk Management. Project subject to formal external Gateway Reviews at key stages.

Services Provided
Braecom's Project Manager acted as Client Side Capital Project Manager from project Inception to Completion (seconded to Belfast City Council by Strategic Investment Board NI) - managing the project through the following phases:

Feasibility & Brief Development Stage (January 2013 - June 2013)
* * * Provision of Cost & feasibility input into Economic Appraisal & Business Case development March 2013.
*
* * * Management of design options appraisal and approval process to select optimum design.
*
* * * Management of feasibility & design capacity study - testing design, budget & programme viability.
*
* * * Preparation and development of Project Brief
*

Design Development Stage (July 2013 - February 2014)
* * * Procurement, appointment Integrated Design Team commission.
*
* * * Procurement & Appointment of Specialist Client Consultants, (Technical & CDMC)
*
* * * Management of Integrated Design Team commission (RIBA Stage A- E)
*
* * * Management of Client User Group / Stakeholder throughout design process
*
* * * Development of Procurement Strategy & Project Execution Plan
*
* * * Development & management of risk management strategy & value engineering process.
*
* * * Programme & Budget management throughout design stage to maintain project viability.
*

Construction Stages
Enabling Civils Works - (April 2014 - August 2014 - Value £0.75m)
* * * Client side management & coordination services diversion enabling project - incl. REC, water mains, sewers, communications (fibre & copper) and gas diversions to free up site for development.
*

Main Contract Works (September 2014 - January 2016 - 15 months - Value £24.5m)
* * * Client side management of main contractor appointment & agreements
*
* * * Coordination on all pre construction and Contractor Design deliverables to enable early site commencement
*
* * * Client User Group Workshops / Stakeholder operational management throughout the design process.
*
* * * Client risk management & reporting.
*

Technical Fit Out Stage (February 2016 - April 2016)
Management of design development, procurement, implementation & commissioning of the following Client items:
* * * Sound Reinforcement System, Production Lighting System, Audio Visual System
*
* * * Digital Signage
*
* * * Catering facilities incl. CPU kitchen & stores Value
*
* * * Moving Ceiling Technical Rigging Grids to Hall 1
*
* * * WiFi coverage for 6000 concurrent device users
*

Commissioning Training & Post Completion Stage
* * * Management of the training & demonstration of systems post completion
*
* * * Post Completion Review
*

Other Services Provided:
* * * *
*
Programme Management
* * * Development, testing, management & reporting of complex project delivery programme for each stage of the capital investment - project delivered on time.
*
* * * Development and implementation of an accelerated programme to deliver the capital works project from inception to completion in 36 mths involving maximum parallel phases to meet stringent funding deadlines.
*
*
Commercial Management
* * * Overall budget responsibility and management for capital investment from feasibility stage to construction close out including Client Change Control process - project delivered on budget.
*
*
Procurement Management
* * * Development of Procurement Strategy & Procurement Plan (for over 20no procurement exercises) including the following key procurements
*
* * * Integrated Design Team (>OJEU Threshold Services) Value >£1.0mil
*
* * * Specialist Client advisors (CDM-C, Technical Advisor & NEC3 Administrator)
*
* * * Main Contract (>OJEU Threshold Works) - Value £24.5mil
*
* * * Technical Equipment (>OJEU Threshold Supplies) - value £1.0mil
*
* * * Loose Furniture (>OJEU Threshold Supplies) - £0.5mil
*
* * * Catering Equipment & Fit Out - £1.1mil
*
*

Click here to view a time lapse of the
Waterfront project

*
Click on images to enlarge
*
Button: Waterfront Thm
*
Waterfront - Elevation from Gregg's Quay
*
Button: Waterfront Thm
*
Waterfront - Elevation from Lagan Embankment
*
Button: Waterfront Thm
*
Waterfront - Front Elevation
*
Button: Waterfront Thm
*
Waterfront - Main Concourse Level 1
*
Button: Waterfront Thm
*
Waterfront - Multi Purpose Hall
*
Button: Waterfront Thm
*
Waterfront - Level 2 Concourse
*
Button: Waterfront Thm
*
Waterfront - Level 2 Meeting Room (1of 6)
*
Button: Waterfront Thm
*
Waterfront - Level 1.5 Board Room (1 of 3)
*
Button: Waterfront Thm
*
Waterfront - Multipurpose Hall 2
*
*
*
*